Panels & Service · October 13, 2026
There are two answers to this question: how long your power is off, and how long the whole project takes from the first call until the utility turns you back on. Here's what decides each one, and what you can do to keep it moving.

How long a panel upgrade takes in Phoenix is one of the first things homeowners ask us, usually right after "what does it cost." The honest answer has two parts. The work itself, when the power is actually off, is part of one day in most cases. The calendar time around it depends on paperwork and scheduling that run through your city and your utility. Knowing which part is which helps you plan, and helps you spot a contractor who is guessing.
Think of a panel upgrade as two clocks running at different speeds:
When someone promises an exact date on the first phone call, they're promising something the city and the utility haven't agreed to yet. We give you a firm date once the utility confirms it.
Every job runs in this order. The length of each step depends on the item on the right.
B and D Electric LLC · banddelectricaz.com
If you want the full picture of who is responsible at each step, our post on who does what in a Phoenix service upgrade breaks down the roles of the homeowner, the contractor, the city and the utility.
Most panel upgrades in the Valley follow the timeline above without surprises. These are the things that stretch it:
This is the part that matters most to most families. For a same-location swap, plan on the power being off for part of one day. Power comes back when the utility reconnects. On some jobs the reconnect happens the same day as the work, and on others the meter stays out until the inspection clears and the utility returns. That depends on your utility, your city and the scope, so we confirm it with you before the work day, not after.
Plan ahead for the hours the power is off:
In a Phoenix summer, a house with no AC gets hot fast, and working on a west-facing meter in afternoon sun is hard on people and equipment. Cooler months make the power-off day easier on your family and give everyone more flexibility if a step runs long. If you already know your panel needs replacing, getting it scheduled before next summer is the easiest way to avoid a no-AC day in July. Our panel upgrades page covers the signs it's time.
Most of Chandler is in SRP territory, though your electric bill is the only reliable way to know your utility. Many Chandler homes were built in the 1980s, 1990s and 2000s, and a lot of them now need more capacity for EV chargers, pool equipment, bigger AC systems and home offices. In HOA neighborhoods, check whether your HOA wants to know about visible changes if the equipment is being relocated or a new disconnect is going on the outside wall.
Chandler's building department lets contractors request inspections online, by text or by phone, and requests made before midnight are scheduled for the next day. That helps keep the inspection step short. You can see how the city handles permits and inspections on Chandler's Building Safety page.
If you're still comparing options, our panel upgrade cost guide explains what drives the price, and the same factors usually drive the timeline.
Text us a photo of your panel, your meter and the top of your electric bill, and we'll tell you what your upgrade involves and what the steps look like for your city and utility, with a free written estimate. B and D Electric LLC is licensed and bonded, Arizona ROC 361086, and our two owners have more than 40 years of combined experience. Call or text (480) 828-1181, or request an estimate.